Project Overview
This project consists of the following development items: 1) Construction of a new retention / detention / treatment pond to support the proposed future development within the SEQ of the Airfield; 2) Construction of a closed stormwater system consisting of pipes and manholes to convey water to the new pond; 3) Relocation of utilities effected by the stormwater system.
Benefits
This project aligns with the Stormwater Master Plans developed for the other quadrants of the Savannah / Hilton Head International Airport as approved by the FAA. Construction of this system will satisfy local jurisdictional requirements for stormwater runoff.
Project Progress
Contract has been awarded to Barnett Southern Corporation, Inc., with a start date of June 28. 2021, and the completion date is set for June 6, 2022.
October 5, 2021 – Excavation for the new stormwater pond is underway.
August 4, 2021 – Contractor is installing temporary fencing in preparation to begin clearing for the new stormwater pond.
January 5, 222 – Pond excavation is about 1/3 complete and Phase 3 storm drain installation is ongoing. Barnett Southern Corporation is the general contractor.
March 31, 2022 – Pond excavation is about 90% complete, Phase 3 storm drain installation is about 65% complete and work began this week on Phase 2 storm drainage. Barnett Southern Corporation is the general contractor. Projected completion is July 2022.
June 21, 2022 – Pond excavation is complete, Phase 3 storm drain installation is about 75% complete and Phase 2 storm drainage is about 60%complete. Barnett Southern Corporation is the general contractor.
October 5, 2022 – The project is complete except for some fencing work, seeding and a few minor punch list items and should be at Substantial Completion next week. Barnett Southern Corporation is the general contractor.