Arrive early. Allow extra time for parking. We will have ample parking available for travelers and will open a remote overflow lot located on Ida J Gadsden Dr. if needed, and will provide a shuttle service to/from the Terminal. When meeting arriving passengers, meeters and greeters are encouraged to use the Airport Cell Phone Lot. The Lot is free, but drivers must stay with their vehicles at all times.
Please allow extra time for parking and plan to arrive at least 2-3 hours prior to scheduled departure time.
Back to Construction Projects

Project Overview

Contractors have begun the initial phase of a major parking expansion project. This project will also encompass filling and grading of some of the low areas between Airways Avenue and Gulfstream Rd. immediately north of the Overflow/Oversize lot.

The current SAV Value Park and the Oversize/Overflow lots will be CLOSED for the duration of the project. In the interim, SAV Value Park will temporarily relocate to the upper level of the south Economy parking deck. Oversize/Overflow vehicles will park at the “Williamsburg” lot on Airways Ave. just this side of the logo berms, with shuttle service provided.

Benefits

When complete, the SAV Value Park lot will more than double in size, and the Oversized/Overflow lot will be paved, lighted, and marked with 827 new spaces.

Project Progress

Reeves Construction Company is the general contractor. As of July 1 construction was 65% complete with final completion expected mid-September.

As of August 1, project is 80% complete.

October 5, 2021
Almost complete, a few punch list items remaining.

 

Project Completed.