Back to Construction Projects

Completed and operational on 01/31/20

Construct an approximate 46,000-square yard aircraft parking apron with associated drainage improvements located on the south edge of the existing terminal apron. This apron expansion is used for overnight aircraft parking which improves the airport’s capacity for aircraft operations and fixed-based aircraft.

Contract Cost = $8MM
Funding – AIP
Consultant – AECOM
Prime Contractor – Holland & Holland, Inc. (WBE, woman owned)
DBE Goal – 5%, currently exceeding our goal at 5.89%
Sub-Contractors:

  • Griffin Contracting, Inc.
  • GLF Construction Corporation
  • Terracon
  • TMC Grassing
  • Trinity Electrical Services
  • Interstate Sealant & Concrete (DBE)